The Saunemin gym/fitness center project is under way. The cold weather has been slowing things up, but we are finally seeing some progress. The footings have been completed. The steel building is here and being erected. The slab will be completed after the building is erected due to the frost. The target date for completion is August, just in time for school to begin next year.
Saunemin Gym Project Forges Ahead